  • Define 3 weather-related ‘use cases’ for analysis and report on the severity and duration of outages and establish the current grid baseline (scenario #1) system performance report (Q2)
  • Hold 2 subject matter expert (SME) meetings to review and validate Duke Energy’s Grid Improvement Plan for resiliency scenario #2 and scenario #3 including advancements in micro and mini grid opportunities (Q3 &Q4)
  • Synchronize with economic (lost wages) modeling
  • Develop matrices including probability distributions, technical and economic consequences
  • Generate valuation of resiliency measures and grid resiliency scenario #3
  • Conduct 2-3 Stakeholder meetings and develop roadmap (Q3-7)
  • Review and validate the list of resiliency advancements in grid scenarios #2 and #3
  • Vet final roadmap before publication